This is how our project progresses.

In Aiana Verde we do not want you to miss any detail, we invite you to be updated in each of the stages of our project, thanks for being part of the change!

10%

2018

At the beginning of 2018, Exergy acquired two properties in Medellin’s downtown with the purpose to develop a new sustainable construction project. Topographic and soil studies were developed, while architectural and structural designs were carried out by consultants and selected professionals. Also, the advertising campaign was carried out by Lobo Agencia. FinallyThe salesroom of the project was adequated and organized to offer information about the project to future buyers.

January- March

In the first quarter of the year,  detailed design of all the netwroks of the project were delivered by designers, as well as the structure and architecture, reaching the point of having the required documents for the fulfillment of all permits, such as urban planning, aeronautics, etc. The integration and coordination of the designs were carried out through the BIM methodology. Also, the analysis and simulation of natural and artificial lighting, sustainability data, and implementation of active measures were carried out.

April – June

In the second quarter of the year, the salesroom decoration and sales pieces started. The delivery of all the documents for the urban office of Medellin was made for a preliminary review, and finally, the opening date of the salesroom was established, which is being worked on during this month (May), by designing and printing the graphic advertising pieces such as sales plans, brochures and the video of the project.

We are preparing everything for you!

July – September

In the third quarter of the year, our salesroom was opened and the sales of properties began. The project management is in charge of Exergy, the construction will be in charge of Obras y Terrenos S.A.S and the fiduciary is in charge of the Alianza Fiduciaria. In addition, the document filed of the construction license application was obtained.

We are waiting for you in our sales room!

Salesroom!

Opening Hours

10.00AM – 6.00PM Monday – Friday

11.00AM – 5.00PM Saturday – Sunday

This error message is only visible to WordPress admins

Error: Access Token for aianaverde is not valid or has expired. Feed will not update.

There's an issue with the Instagram Access Token that you are using. Please obtain a new Access Token on the plugin's Settings page.
If you continue to have an issue with your Access Token then please see this FAQ for more information.

Error: No posts found.

Make sure this account has posts available on instagram.com.

Error: admin-ajax.php test was not successful. Some features may not be available.

Please visit this page to troubleshoot.